Sunday 5 July 2009

Allerton Cottage

Week 7.

The beam & block flooring has been completed and the gable end wall has been exposed to allow us to begin installing the main supporting beams which weigh nearly 3/4 of a tonne.


The opening for the 4.7 metre bi-fold doors has been formed to the rear of the coach house.








No comments: