Sunday 5 July 2009

Allerton Cottage

Allerton Cottage is a 26 week project commencing from 20th April and completing on 16th October.


Week 3.


The link between the existing house and the coach house has been demolished.

The coach house roof has had some lightweight strengthening.


Below ground drainage alterations have taken place.

Footing are being dug and stud walls to coach house have been built.

Where possible we have saved materials for future re-use or recycling.