Master Bathroom / wetroom is completed
Spiral staircase is installed to allow access to mezzanine
Living room floorboards are replaced, filled and resanded
Generally all works and snags to main house completed
Kitchen / dining area moves on
Week 10.
The brickwork to the kitchen atrium has been completed, the atrium joists have been installed.
The kitchen and atrium roofs have been made watertight.
The roof has been stripped above the existing kitchen where the 1st floor extension is to be built, the joists and deck have been installed and the brick work is starting to go up.
Week 5.
The kitchen outrigger has been demolished, the new link walls have been partly built and the beam & block floor partly installed.
Part of the coach house wall was deemed by our engineer to be dangerous, so it was taken down and rebuilt.
The centre section of the coach house including the dorma window was stripped out to allow us to install a steel post and beams to carry the new staircase.
Allerton Cottage is a 26 week project commencing from 20th April and completing on 16th October.
Week 3.
The link between the existing house and the coach house has been demolished.
The coach house roof has had some lightweight strengthening.
Below ground drainage alterations have taken place.
Footing are being dug and stud walls to coach house have been built.
Where possible we have saved materials for future re-use or recycling.